Planning case study · School place planning
Housing growth translated into school place need
Bolton Council · Infrastructure Delivery Plan evidence
Coplug's spatial reasoning agent gave Bolton Council a granular analysis of how over 14,000 planned homes translate into additional education places across early years, primary, secondary, post-16 and special needs, by school planning area and site.
Localised impact
1 / 5
school planning areas accounts for nearly half of the additional places from housing
- 14,000+
- homes in the trajectory to 2042
- 16 yrs
- plan period, beyond the 5-year school place horizon
- 5
- education phases, early years to special needs
- 2
- forecasts: ONS baseline and housing-led
- Days
- from housing trajectory to evidence, not months
- 8
- data sources, including detailed DfE pupil yield standards and calculator
The need
Challenge. Evidence of the education places arising from planned housing growth, by phase and school planning area, set against existing school capacity. The ONS projection shows the school-age population falling over the plan period; housing growth offsets part of that fall and concentrates new demand in particular areas.
Why it was hard. School place planning typically looks five years ahead, while the Local Plan needs the impact of growth across the full plan period. Pupil demand also depends on housing mix as much as the number of homes, with larger family and affordable homes generating significantly more places than smaller flats. Published projections take limited account of housing delivery and stop at borough level.
Driver. Infrastructure Delivery Plan and school place planning.
What Coplug delivered
- Housing growth by site, tenure, type, size and year
- Pupil yield by phase, from the housing mix: early years, primary, secondary, post-16 and special educational needs
- Housing-led projections of the school-age population
- Demand by school planning area and five-year band to 2042
- Existing capacity reviewed against current pupil numbers
Decision and impact
Decisions supported. Where additional school provision may be required, in which phase and when, and which sites drive demand, beyond the five-year school place planning horizon.
Outcome. Evidence produced within days of receiving the housing trajectory, rather than months of back-and-forth between council and education partners. A view of school demand across the whole plan period, showing a second, stronger period of demand in the 2030s as the major allocations deliver, beyond the reach of five-year forecasts. Housing demand is concentrated where existing headroom is smallest, distinguishing areas under pressure from those able to absorb growth. When the trajectory was revised, the updated evidence was produced rapidly, showing how a shift in housing mix changes school demand even where dwelling numbers do not.
Housing growth and primary schools

The report

Primary-age population: two forecasts

Backed by industry-validated calculators, using Department for Education pupil yield data, ONS projections and council school capacity data.